Key Projects

Happy Valley

Happy Valley

12.825 MWp
375 5B Mavericks

5B deployed in 2021, taking
12 weeks
on site with 
2 teams of 3

Colon

Colon

1.9 MWp
62 5B Mavericks

5B deployed in 2020, taking
10 days
on site with a
team of 7

Port Bonython

Port Bonython

2.12 MWp
62 5B Mavericks

5B deployed in 2019, taking
21 days
on site with a
team of 3

Carosue Dam - Phase I

Carosue Dam - Phase I

1.0 MWp
35 5B Mavericks

5B deployed in 2020, taking
15 days
on site with a
team of 3

Moomba Oilfields

Moomba Oilfields

1.2 MWp
100 5B Mavericks

5B deployed in 2019 across 20 sites, taking
2 days per site
on site with a
team of 3