9MW Fortescue Cloudbreak, WA

Written by 5B | Aug 31, 2025 2:15:00 PM

 

Solution

5B supplied 9 MW of its Maverick Solution for Fortescue’s Cloudbreak solar farm, the first time that the Tier 1 miner has used 5B Mavericks. Fortescue selected the 5B Maverick system to assess the system’s performance in the Pilbara’s remote high-temperature environment and confirm its potential to deliver fast, cost-effective renewable energy installations. Speed of deployment is an important factor for Fortescue, which is working towards achieving Real Zero emissions by 2030.

5B onboarded Pilecom as a new deployment partner to deliver the project. Pilecom was able to achieve the fastest Maverick deployment speed of 1 MW (20 Mavericks), unfolded in one day with a crew of four people (after site prep, e.g. markout, piling, unloading).

The 168 Mavericks were produced at 5B’s Adelaide facility. The Cloudbreak solar farm is part of a broader Fortescue initiative to develop a Pilbara Solar Innovation Hub, co-funded by the Australian Renewable Energy Agency (ARENA).